Traffic Engineering Design Plans

The Los Angeles Department of Transportation supervises the review of all temporary street, lane, and sidewalk closures. Traffic engineering design plans differ based on if they are less or more than 72 hours.

Short-Term Closures
Short-Term Closures

CITYWIDE TEMPORARY TRAFFIC CONTROL

The CTTC Division of the City of Los Angeles Department of Transportation reviews and oversees implementation of short-term (less than 72 hours) Temporary Traffic Control Plans. Our function is to ensure Contractor compliance with Federal and State principles and standards when implementing Temporary Traffic Controls (TTC) on City Right-of-Way. This is intended to provide for the safe and efficient movement of road users through and around TTC zones while reasonably protecting users, workers, and equipment in accordance with the California Manual of Uniform Traffic Control Devices, CAMUTCD, Part 6 (Latest Edition). This page provides guidance & information needed to submit Worksite Temporary Traffic Control Plans to the CTTC Division. These items will assist our team in understanding the nature of your work and help us in providing a quick turn-around time for our review.

 

Important Note:

Before the initiation of a new request, please read the following WTCP requirements to determine if your design should be a Professionally Prepared WTCP or if an Engineer Designed WTCP is required.

 

Click here to initiate a review of your Worksite Traffic Control Plan (WTCP)

Long-Term Closures
Long-Term Closures

A closure that includes striping changes and/or K-rails for over 72 hours continuously is considered “long-term”. The Los Angeles Department of Transportation’s ‘Permit Plan Review’ section reviews long-term temporary traffic control plans and temporary signal plans.

Temporary traffic control plans are designed to provide for the safe and efficient movement of traffic through and around work zones for large projects that require the long term use of the City’s right-of-way. Large project work zones typically include street, travel lane, parking lane, alley and/or sidewalk closures.

All temporary street, travel lane, parking lane, alley and/or sidewalk closures require a permit issued by a City of Los Angeles permitting agency. The two permitting agencies are: 

  • Bureau of Engineering (BOE)
  • Bureau of Street Services (StreetsLA)

The permitting agency determines the need for a worksite traffic control plan-set reviewed and accepted by LADOT's Permit Plan Review Section.

 

Plan Submittal & Plan Check Process

The Permit Plan Review Section requires a first submittal meeting for all temporary traffic control, traffic signal, and geometric plan submittals. The meeting allows the plan check engineer to understand the project requirements, development layout and impact, and project timelines.

Request a Submittal Meeting

Temporary Traffic Control Plan Sample [.pdf] [.dwg] 
 

Visit the Technical Reference Library for links to Standards and Specifications.

Technical Reference Library

Visit the Plan Review Checklists webpage for checklists, flowcharts and other sample plans.
Plan Review Checklists